FORM B

PROJECT DESCRIPTION AND LOCAL SHARE IDENTIFICATION

FY 2002 Municipal Capital Project Matching Grant Program

As approved by KPB Resolution 2000-084

Please provide the following information for each of your FY 2002 Capital Matching Grant Project(s). All questions within Form B must be answered for each project or the application will be returned.

1. GRANTEE NAME: Kenai Peninsula Borough

2. Priority No. 1

PROJECT TITLE: Road Service Area - Road improvement program

3. LOCAL SHARE: Identify and explain the sources of the local share, which can be a contribution of materials, paid labor, equipment usage, land, or cash. If cash, tell us where the funds come from, because they must be funds from non-state sources, with the exception of safe communities.

The local matching requirement will be satisfied through local tax sources provided by the Road Service Area.

FY 2002 Requested Amount $ 751,296

Local Share Amount 321,984

Project Total $ 1,073,280

Because of the nature of our program, we are requesting more than the amount recommended by the Dept. of Community and Economic Development. We acknowledge that not all of the road projects on our list can be funded under this grant program. However, requesting more than the anticipated amount provides the Borough flexibility in completing its projects. If for some reason a project cannot be initiated or completed as originally anticipated, road crews can immediately proceed to the next project on the list. Projects will be completed in priority order until grant funds are depleted. Remaining projects will be completed under future grant programs or the Road Service Area's normal process.

GRANTEE NAME: Kenai Peninsula Borough

4. PROJECT DESCRIPTION:

a) What is the purpose of the project?

Our project will provide improvements to local roads. This will be a continuation of the road improvement program started in 1995 with FY'94 funding through the Capital Matching Grant Program. The recommendations for FY 2002 road improvement projects were approved by the Road Service Area Board of Directors at their meeting on September 19, 2000, and by the Borough Assembly through adoption of Resolution 2000-084. A detailed description of the projects within each region is included herein. The projects, broken down by regions within the Borough, are shown below:

Central Region 24 roads $ 406,040

East Region 11 roads 85,680

North Region 11 roads 197,440

South Region 21 roads 384,120

TOTAL $ 1,073,280

b) What has been accomplished to date?

This is the seventh year of using state and local funds under the matching grant program for our local road improvements. Improved roads provide safer driving conditions for our residents, plus reduces our cost for general road maintenance.

c) How will this grant be used - what exactly will be accomplished at completion of this grant? (After reading this description, DCED should know what activities will need to take place, in what order, and have a strong sense that the grant recipient knows the project and will be able to accomplish the tasks necessary for successful completion.)

This grant is to continue our road improvement program. All grant funds will be used for contract services. The soonest contracts could be bid, using FY 2002 funding, would not be until the spring of 2002. Types of projects include resurfacing, hydroaxing, ditching, and drainage correction. The Road Service Area Board has divided the Borough into four areas; central, south, north, and east. Projects on the list include roads in each area, in priority order. This is to assure all areas of the Borough receive the benefits of this grant program.

d) If other funds are needed to complete the project, list the sources of other funding, and tell whether each source is confirmed, awarded or in an application review process. Also tell what the total project cost is anticipated to be.

Grant funds are used to supplement the Road Service Area funds. The Road Service Area has a 1.0 mill levy, which generates approximately $2.4 million per year. Additional funding for roads is received through the State revenue sharing program. Road improvements are never ending, therefore it is impossible to determine a total project cost. Whatever funds are provided under the FY 2002 matching grant program will be used for Borough roads.

e) What are the estimated start and finish dates of the project?

Road improvements are a continuing, ongoing process. Specific projects for FY 2002 will begin as soon as funding is available. Projects on the list will be completed as funding allows and prior to the termination date of the grant.

Capital Improvement Project List for Roads

Approved by Road Service Area Board on September 19, 2000

SOUTHERN REGION

ROAD ESTIMATED
PROJECT No.

ROAD NAME

RD ID# LENGTH

COST

FY02-S1 David St

725

1050

$8,400.00

Sharon St

3680

1000

$8,000.00

Peggy St

2029

1325

$10,600.00

FY02-S2 Holly St

1222

5280

$42,240.00

Oil Well

4949

5280

$42,240.00

FY02-S3 Echo Dr

827

1000

$8,000.00

Dusty Ave

797

700

$5,600.00

Elenia St

851

1850

$14,800.00

Honorable Dowling

3303

1050

$8,400.00

FYO2-S4 Sary Sue

3662

2900

$23,200.00

David Lee St

724

1100

$8,800.00

FY02-S5 Agusta Lane

19

2100

$16,800.00

Eagleview

3162

3700

$29,600.00

FY02-S6 Mary Lane

1744

2600

$20,800.00

Dorothy Dr

780

3950

$31,600.00

FY02-S7 Fernwood

917

2900

$23,200.00

Greer, Lower

1110

500

$4,000.00

Kalopi Ct

1410

500

$4,000.00

FY02-S8 Voznesenka 5280

$42,240.00

Lowbush

1651

1850

$14,800.00

Mossberry Ave

5359

2100

$16,800.00

Southern Region Total

$384,120.00

Capital Improvement Project List for Roads

Approved by Road Service Area Board on September 19, 2000

NORTHERN REGION

PROJECT No.

ROAD NAME ROAD ID ROAD LENGTH ESTIMATED COST
FY02-N1 Tenakee Lp

2613/5395

1700

$13,600.00

English Av

863/3184

2100

$16,800.00

Ramona St

2128

2400

$19,200.00

FY02-N2 Nurimi Dr

5402

250

$2,000.00

Ylmaki Dr

2904

1000

$8,000.00

Kivi Lake Rd

5095

750

$6,000.00

FY02-N3 Lighthouse Ave

1597

1350

$10,800.00

Rozella Dr

2254

1350

$10,800.00

FY02-N4 Seascape St

2333

4500

$36,000.00

FY02-N5 Northwoods St

5041

4000

$32,000.00

FY02-N6 Bastien Dr

2996

5280

$42,240.00

Northern Region Total

$197,440.00

EASTERN REGION

PROJECT No.

ROAD NAME ROAD ID ROAD LENGTH ESTIMATED COST
FY02-E1 Caribou Heights Cr

1901

900

$7,200.00

Hemlok Ct

5302

600

$4,800.00

Towle Ave

2675

400

$3,200.00

Patrica Ln

5271

620

$4,960.00

Edwards St

843

200

$1,600.00

Lisa Ave

3423

$4,800.00

Kasulka cr

3362

400

$3,200.00

FY02-E2 Palmer Creek Rd

4470

5540

$44,320.00

FY02-E3 Knight St

1489

1000

$8,000.00

Tower Cir

7228

250

$2,000.00

Turret Cir

5151

200

$1,600.00

Eastern Region Total

$85,680.00

Capital Improvement Project List for Roads

Approved by Road Service Area Board on September 19, 2000

CENTRAL REGION

PROJECT No.

ROAD NAME ROAD ID ROAD LENGTH ESTIMATED COST
FY02-C1 Moose Ridge Ave

4842

3600

$28,800.00

Kyee St

3389

500

$4,000.00

Ashley Ave

117

925

$7,400.00

FY02-C2 Edgington Rd

757

6300

$50,000.00

FY02-C3 Dudley Ave

791

1150

$9,200.00

Jones St

1353

1700

$13,600.00

Hallelujah Tr

4861

400

$3,200.00

Hallelujah Ct

5291

350

$2,800.00

FY02-C4 Lakeview St

1543

3525

$28,200.00

Water St

2780

950

$7,600.00

Water Ct 550

$4,400.00

FY02-C5 Kalgin Av

1384

3550

$28,400.00

Kalgin Ct 500

$4,000.00

Reef

4903

600

$4,800.00

FY02-C6 Resolution Dr

2165

2800

$22,400.00

Discovery Dr

763

1575

$12,600.00

Ruby Dr

2256

2300

$18,400.00

FY02-C7 Valley View Rd

3819

5280

$42,240.00

FY02-C8 Salmon Dr

2279

1650

$13,200.00

Salmon Cr

2277

600

$4,800.00

Rainbow Dr

2118

4800

$38,400.00

FY02-09 Anna Lane

4751

2000

$16,000.00

Fair Game

895

1200

$9,600.00

Otter Trail

1968

4000

$32,000.00

Central Region Total

$406,040.00

GRAND TOTAL

$1,073,280.00