Tree Hazard Reduction at Borough Facilities
4 man crew @ 16.00/hour = 162.00/man X4= $648.00/day
FACILITY: | AREA(S): | CREW
DAYS: |
EST. LABOR: | DISPOSAL/
SUPPLY: |
Nikiski Elementary | Around sports field, North end property, between entrance & exit | 8 | $ 5,184 00 | $ 1,607.04 |
Nikiski H/S | Entry road, around sports fields | 10 | $6,480.00 | $ 2,008.80 |
North Star | Entry road (public) between entrance & exit, around sports field | 8 | $5,184.00 | $ 1,607.04 |
Kenai Central (KCHS) | Highway end of sports fields | 4 | $2,592.00 | $ 803.52 |
KCHS - Voc. Ed Bldg | Around building and parking lot | 4 | $ .00 | $ 803.52 |
Kenai Elementary | Bluff end of property | 3 | $1944.00 | $ 602.64 |
Kenai Middle School | Highway end of school | 3 | $1,944.00 | $ 602.64 |
Mountain View | Around sports field | 4 | $2,592.00 | $ 803.52 |
Sears | Around play grounds & parking lots | 4 | $2,592.00 | $ 803.52 |
K- Beach | Around play grounds & parking lot | 8 | $5,184.00 | $ 1,607.04 |
Soldotna Maintenance Shop | Around new lot | 3 | $1,944.00 | $ 602.64 |
Sterling | By sled hill & new parking lot | 2 | $1,296.00 | $ 401.76 |
Tustumena | Between entrance & exit, around sports fields & by generator bldg. | 10 | $6,480.00 | $ 2,008.80 |
Borough Admin. BI | N/A | |||
Redoubt Elementary | Around new parking lot & sports field to SOHI | 12 | $7,776.00 | $ 2,410.56 |
S D Warehouse, Media Center | N/A - brush out antenna farm | 6 | $3,888.00 | $ 1,205.28 |
Skyview | ntry road, around sports fields, along trail system | 12 | $7,776.00 | $ 2,410.56 |
SOHI | River end of parking lot to sports fields/ Redoubt elem. | 10 | $6,480.00 | $ 2,008.80 |
Soldotna Elementary | N/A $ - $ | |||
Soldotna M/S | N/A $ - $ | |||
Out of town schools add per them @ 80.00/man/day | ||||
Cooper Landing | Around parking lot & service roads, along hillside | 6 | $4,208.00 | $ 1,304.48 |
Hope | Around fields & creekside | 4 | $2,912.00 | $ 902.72 |
Moose Pass | Around sports field | 2 | $1,616.00 | $ 500.96 |
Seward Elementary | Around sports field | 8 | $ 5,504.00 | $ 1,706.24 |
Seward H/S | Behind school, around H/S parking lot to Baseball field | 8 | $5,504.00 | $ 1,706.24 |
Chapman | Tree removal in play field | 2 | $1,616.00 | $ 500.96 |
Homer H/S | Behind school and creekside | 12 | $8,096.00 | $ 2,509.76 |
Homer M/S | Along highway in front of school/parking lot, around soccer field | 12 | $8,096.00 | $ 2,509.76 |
Homer Maintenance Shop | N/A | |||
Kachemak Selo | N/A | |||
McNeil Canyon | Along town side of property and from ball field to creek (by well house) | 12 | $8,096.00 | $ 2,509.76 |
Nanwalek | N/A | |||
Nikolaevsk | Behind school | 6 | $4,208.00 | $ 1,304.48 |
Ninilchick | Along bluff | 3 | $2,264.00 | $ 701 .84 |
Pau]Banks | Around improved school grounds | 3 | $2,264.00 | $ 701.84 |
Port Graham | Around school building | 4 | $2,912.00 | $ 902.72 |
Port Graham | Around school building | 4 | $2,912.00 | $ 902.72- |
Susan B. English | N/A | |||
West Homer Elementary | 2 | $1,616.00 | $ 500.96 | |
Equipment Purchase | Stump grinder, Chipper/shredder | $ 18,500.00 | ||
Estimated costs Total Estimated costs
|
|
$130,840.00
|
$ 59,060.40
$ 189,900.40 |