SUBJECT: Resolution 2005-048, Award Of Contract For Kenai Central High School Roof Replacement, Sections "C" And "D"
The Purchasing and Contracting Department solicited and opened bids for this capital project on May 25, 2005. Two (2) bids were received and are recorded in the bid tabulation attached. The Invitation to Bid was published in the Anchorage Daily News on May 8, 2005 the Peninsula Clarion on May 4, 6 and 10, 2005, and the Homer News and the Seward Phoenix Log on May 5, 2005.
The project consists of providing all labor, materials and equipment to replace approximately 10,500 SF of roofing at Kenai Central High School. The work includes the demolition of existing roofing and the installation of new rigid insulation and built up roofing, in addition to approximately 415 LF of new parapet construction.
The attached resolution requests award of contract for this work to Rain Proof Roofing, LLC, for the total bid of $206,000.00.
The funding for this project is from the Capital Improvement Projects budget. All expenditures for this project will be charged to account number 400.73020.05713.
Attachments: Resolution
Bid Tabulation