KENAI PENINSULA BOROUGH
P. W. / MAJOR PROJECTS DIVISION
47140 E. POPPY LANE, SOLDOTNA, AK. 99669
PH:(907) 262-9657 FAX: (907) 262-6090
MEMORANDUM
TO: Gary Superman, Assembly President
Kenai Peninsula Borough Assembly Members
THRU: Dale Bagley, Mayor
Mark Fowler, Purchasing & Contracting Officer
Walter Robson, PW/MPD Director
FROM: John Hedges, Project Manager
DATE: March 24, 2005
SUBJECT: Resolution 2005-026, Authorizing Award of Contract for the Special Inspection and Quality Assurance Testing Services, Group A, for the Central Peninsula General Hospital, Phase 2
The Purchasing and Contracting Office solicited and opened proposals for the above-referenced project on March 22, 2005. The Request for Proposals was advertised in the Peninsula Clarion, Homer News and Seward Phoenix Log.
Three responsive proposals were received on March 22, 2005. The Evaluation Committee members individually reviewed and scored the proposals based on criteria contained in the RFP. The results are summarized as follows:
Company Total Score
Alaska Structural Insp., LLC 277
Northern Geotechnical Eng., Inc. 274
Northern Test Lab 268
The attached resolution requests award of contract for this work to Alaska Structural Inspection, LLC as the high score firm for the amount of Thirty Six Thousand One Hundred Seventy Six Dollars and forty Cents ($36,176.40) .
The scope of work shall consist of all special inspections that relate to soil compaction and site preparation, reinforcing steel, reinforcing concrete, and bolts installed in concrete. The consultant will be expected to perform their services from April 11, 2005 to September 1, 2006.
Funding is available in the CPGH bond capital project's budget. Expenditures for the project will be charged to account number 401.81111.04CHB.43011.
Attachments: Resolution 2005-026
Score Sheet